The services included the preparation of a feasibility study, ESIA, conceptual/ detailed design and bidding documents for the WWTP (0.6 Mio. PE, 100,000 m³/d) and Network (main pumping station 12.000 m³/h, 110 km gravity lines, 8 km pressure lines, two new lifting stations, enlargement of four existing pumping stations), assistance in tendering and construction supervision.

Water & Environment
Preparation of a Masterplan and Feasibility Study for the Project Sewage Disposal Kosovo I/II
The Objective of the Project was to improve the collection and treatment of wastewater, as well as the management of storm water.