The services included the turnkey design and superstructure management of the new WWTP in Mersin (1.05 million PE, 190.000 m³/day) including a sea outfall (2000 mm, 2 km), and measures in the wastewater network (total 84 km), sewage force mains (2x DN 1600, total 21 km), and rehabilitation and upgrading of 10 pumping stations.

Water & Environment
Feasibility Study Water Supply using compact plants for rural area in the provinces Navoi and Samarkand
Preparation of a Feasibility study with the aim to investigate options for immediate potable water supply using containerized water treatment facilities to relieve the grave supply situation in Samarkand and