The services included the preparation of a feasibility study, ESIA, conceptual/ detailed design and bidding documents for the WWTP (0.6 Mio. PE, 100,000 m³/d) and Network (main pumping station 12.000 m³/h, 110 km gravity lines, 8 km pressure lines, two new lifting stations, enlargement of four existing pumping stations), assistance in tendering and construction supervision.

Water & Environment
Technical Audit of WW collection & treatment systems in North Macedonia, preparation of documents for Supply of Water Equipment for Radovish, Kichevo, Strumica, Prilep, Berovo, Kumanovo, Bitola & Tetovo
The overall objective to which this action contributes ism to minimize the adverse effects of inappropriate wastewater and sewage sludge management in larger North Macedonia’s agglomerations.