The services included the preparation of a Feasibility Study, Conceptual and Detailed Design, bidding documents, and assistance during tendering and supervision of the water supply network (including new well field area, water reservoirs, main pumping station, transmission main, 20 km new network), the stormwater network (including 4 retention basins, rehabilitation and extension of existing main storm water drains ca 17,4 km), the wastewater network (including ca. 17 km pipelines), and the WWTP (300.000 PE; 61.000m³/day).
![Camp Marmal, Mazar-e-Sharif – Water Treatment, Water and Wastewater Network](https://srp-international.com/wp-content/uploads/2014/02/SRP-REF_afgan-300x100.jpg)
Water & Environment
Camp Marmal, Mazar-e-Sharif – Water Treatment, Water and Wastewater Network
The project included the preparation of the conceptual design, detailed design, and bidding documents, and the provision of supervision services for the entire water supply treatment/ distribution system, as well